Question
When the beam/arc order in Compass measurements is different than the TPS plan, for example beam 2 was delivered before beam 1. The beam assignment will be wrong in Compass like below.
How to assign the measurement correctly?
Answer
Please follow the steps below to re-order the beams/arcs.
Step 1
Assign the measurement to the plan, and then right click on the measurement, select Recorder beams...
Step 2
The Records Beams window jumps out. Here you can change the order of the beams as you need.
Step 3
Click OK when finish. Now the beam/arc order should be correct.